This National Audit Office report examines the Ministry of Defence’s management of its large and complex infrastructure projects at nuclear-regulated sites. It assesses whether the Department works with site operators and regulators to produce cost-effective designs; if commercial arrangements transfer risks; and how these projects are managed. None of the three projects in our review will be delivered to their original timeframe, with delays of between 1.7 to 6.3 years, and a combined £1.35 billion cost increase. The projects all experienced cost increases and delays in their early stages, with projects for CPC facilities and MENSA being re-scoped.